1 of 2Dinning Room Floor and Counter Tops
The dinner room floor with the 800 pilot holes drilled
All pieces are fitted and ready to be attached to the floor
Laying the thin coat
This is the first row of 5 rows
The backer board is numbered and will be set back in place and screwed to the floor
We stopped late Wednesday evening
Same status but from a different angle
What a mess!
The counter top on top of the wine cooler
North wall counter top
The island
South wall
Early Firday morning as they where putting in the counter tops we finished laying the backer board


Spreading the thin coat
November 17-21, 2008